Baker Water Treatment Plant

Baker Water Treatment Plant

The Baker Water Treatment Plant is a 28.1 million gallon per day (mgd) drinking water treatment plant at the site of the former Baker Filtration Plant in the City of Lake Forest.  The project was a joint regional project by five South Orange County water districts, supported by community and business organizations.

Baker_cropped.jpg

 

Updated June 14, 2017

Status: The plant is now online and operational 24-hours a day.

Note: There continues to be some minor construction finish work activity and you may hear construction noise during approved hours. (7am - 8pm Monday - Friday, 8am - 5pm Saturdays.  In addition, IRWD will be performing sound monitoring work on Thursday June 22 and Friday, June 23 and residents may see some activity on Wisteria Lane from midnight to 6:00am on both days.

Contact information: For questions or concerns, please email info@irwd.com or call 949-453-5500. For emergencies during non business hours please call 949-453-5300 (24 hours) as email is not monitored after hours.

------------------------------------------

Increased Water Supply Reliability:

The plant provides increased water supply reliability to South Orange County by increasing local treatment capability from multiple water supply sources, including imported untreated water from the Metropolitan Water District of Southern California (MWD) through the Santiago Lateral and local surface water from Irvine Lake.

Protection in Emergencies:

The plant provides a reliable local drinking water supply during emergencies or extended facility shutdowns on the MWD delivery system. It will also increase operational flexibility by creating redundancy within the water conveyance system

Improved Water Quality:

The plant uses advanced microfiltration treatment and ultraviolet disinfection technologies to produce water that meets standards stricter than current regulatory requirements, resulting in a consistent, high quality source of drinking water for South Orange County.

Sustainable and Efficient:

The plant was designed to minimize waste through on-site recycling and treatment of waste streams, resulting in a 99% recovery efficiency.

Complements the Community:

Consistent multi-agency involvement and collaboration throughout the plant's planning and design phases resulted in a project which is architecturally designed to blend into the surrounding neighborhood.

Project Ownership:

El Toro Water District (ETWD), Irvine Ranch Water District (IRWD), Moulton Niguel Water District (MNWD), Santa Margarita Water District (SMWD) and Trabuco Canyon Water District (TCWD)  each own capacity rights in the Baker WaterTreatment Plant’s 28.1 mgd production capacity. The plant produces enough water to serve 63,300 homes within South Orange County, and provides an additional source of reliable, high quality drinking water to the region.

Water Reliability Improvement:

Capacity Rights by Agency web

South Orange County receives the majority of its potable water from the Municipal Water District of Orange County via MWD’s Diemer Filtration Plant and the Allen-McColloch Pipeline. For a number of years, water agencies in SouthOrange County have investigated alternatives for improving both water supply and water system reliability.

In 2001, IRWD consolidated with the former Los Alisos Water District which served most of the City of Lake Forest.

The original Baker Filtration Plant was one of the facilities IRWD took ownership of in the consolidation. In 2006, the project partners studied the feasibility of constructing a new regional water treatment plant at the site of the former Baker Filtration Plant.

After evaluating all critical issues including source water quality, treatment alternatives, permitting requirements, the site, and project economics, the project partners determined that the Baker Water Treatment Plant was an excellent option for improving South Orange County’s water reliability and for developing alternative local water supplies for the region.

The project was awarded to PCL in December 2013, and broke ground in February 2014. Overall cost of the project is $103.6 million. It is expected to be online in early 2017 and will be managed and run by IRWD.

Documents:

Baker Water Treatment Plant Fact Sheet

Environmental Impact Report

Other Projects in the Area:  Trabuco Canyon Water District project (Serrano Creek area)
 Baker Photos:

Baker Inside 1.jpg

Baker Old Sign.jpg

Baker Inside 2.jpg

Baker Overview.jpg

Save

Save

Latest News

energy-storage-award
IRWD Wins Innovation Award For Energy Storage ProgramThe IRWD Energy Storage Project was recently selected as a winner at the 6th Annual Golden Hub of Innovation Awards by the Association of California Cities - Orange County (ACC-OC). The Golden Hub of Innovation Awards recognizes local agencies, cities and...
irwd-professionals-assure-water-quality-2
IRWD Professionals Assure Water QualityWhen it comes to delivering safe water to our customers, the bottom line is that Irvine Ranch Water District meets or exceeds all state and federal guidelines for drinking water. Ensuring that quality on a day-to-day basis is the primary responsibility...
posters-chosen-for-annual-contest
Posters Chosen for Annual ContestFive posters created by students who attend school in the Irvine Ranch Water District service area were selected for judging in the Metropolitan Water District of Southern California’s “Water is Life” poster contest. IRWD judges selected the posters from among many...