Main Street Diversion Project

Main Street Diversion Project

The Main Street Diversion Structure routes sewage to the IRWD Michelson Recycled Water Plant and is located in San Mateo Park in the city of Irvine. This small structure has developed a slight tilt that makes it necessary to level the building. The project will install micro-piles and grade beams to level the building. This project will be completed in the spring.

Contact information: For questions or concerns, please email info@irwd.com or call 949-453-5500. For emergencies during non business hours please call 949-453-5300 (24 hours).

 Main Street Diversion

 

 

 

 

 

 

 

 

 

 

What's Going on Now:

Week of June 19, 2017:

Work continues on the PLC panel. Acceptance of consruction is anticipated on July 24.

Week of May 22, 2017:

The contractor completed work this week. Park access has been restored. Final acceptance will take place at the June 26 board meeting.

Week of May 8, 2017:

Construction is expected to be completed within two weeks with final acceptance in June. The contractor completed the grade beams, installed the grout under the building, installed the air-tight hatch and replaced the slide gate operator. Installation of the final item, the PLC, is in progress.

Week of April 24, 2017:

Construction should be complete in mid-May, with final acceptance in June. The subcontractor completed micropile installation on April 21. Pacific Hydrotech is in the process of forming the grade beams. Items to complete include installation of the air-tight hatch and the slide gate operator.

Week of April 10, 2017:

An unexpected subsurface void was encountered while drilling the first micropile and caused the building to subside and tilt. A 3-inch wide surface fissure in the soil behind the building also developed. Staff requested the assistance of NMG Geotechnical; they recommended drilling nine exploratory holes to determine the extent of the void and filling the holes and the void with two-sack slurry.

Week of March 27, 2017:

The sub-contractor installed the test piles and they passed the compression test. A smaller drill rig was brought in and production piles were installed. The contractor is installing the grade beam rebar, dowels, and forms.

Week of March 13, 2017:

The contractor leveled the building with hydraulic jacks, removed the jacks, and installed temporary supports. Pacific Hydrotech anticipates installing the piles next week.

Week of March 1, 2017:

The contractor mobilized last week and installed project signs and temporary construction fencing.

Latest News

energy-storage-award
IRWD Wins Innovation Award For Energy Storage ProgramThe IRWD Energy Storage Project was recently selected as a winner at the 6th Annual Golden Hub of Innovation Awards by the Association of California Cities - Orange County (ACC-OC). The Golden Hub of Innovation Awards recognizes local agencies, cities and...
irwd-professionals-assure-water-quality-2
IRWD Professionals Assure Water QualityWhen it comes to delivering safe water to our customers, the bottom line is that Irvine Ranch Water District meets or exceeds all state and federal guidelines for drinking water. Ensuring that quality on a day-to-day basis is the primary responsibility...
posters-chosen-for-annual-contest
Posters Chosen for Annual ContestFive posters created by students who attend school in the Irvine Ranch Water District service area were selected for judging in the Metropolitan Water District of Southern California’s “Water is Life” poster contest. IRWD judges selected the posters from among many...